Page 37 - Final Noosa Cycling and Walking Strategy and Implementation Plan 2020 - 2040
P. 37
Project types
Noosa has a network of 240kms of sealed paths and 153kms of cycle routes, however, to create a connected and safe network
more infrastructure is required. A total of 453 infrastructure projects have been recommended for implementation. Of these, 173
involve upgrades to existing facilities (approximately 99km) with the other 280 being new facility projects (approximately 208km).
Figure 12 summarises the 453 projects into their project types.
Figure 12: Infrastructure type Figure 13: Number of projects by network type
Prioritisation
A set of scoring criteria were developed in consultation with the PRG to prioritise the 453 projects. The projects were individually
scored against each of the criteria, with the total score for all criteria used to determine its priority. The scoring criteria and
associated weightings are provided in Figure 14.
Figure 13: Assessment criteria
37