Page 22 - Final Noosa Cycling and Walking Strategy and Implementation Plan 2020 - 2040
P. 22

Key non-infrastructure and further planning tasks supporting each action and the time frames in which each task is to be
         completed are outlined below.


         Action 1. Deliver and maintain a safe and connected network


                                                                            Short        Medium
                                                               In
          Task                                                              Term         Term        Ongoing
                                                               progress
                                                                            (by 2026)    (by 2031)

          1.1 Implement the prioritised bike riding and walking network plans   ✓                      ✓
          developed as part of the NCWSIP.

          1.2 Develop a detailed Trails Masterplan and Implementation Plan
          that expands on Tourism Noosa's Noosa Trail Masterplan 2020. A
          coast to hinterland trail will be investigated as part of this plan. The   ✓
          master plan will identify upgrades to existing trails, potential new
          trails and an implementation plan.

          1.3 Identify priority locations for the construction of safe pedestrian
          and bike crossings for all abilities, including bridges and         ✓
          underpasses.

          1.4 Investigate new and innovative safe design solutions for
          pedestrian/ cyclist priority crossings at intersections (eg raised   ✓
          priority pedestrian /cycle crossing, roundabout treatments), and pilot
          treatments which are safe and meet Noosa design principles.

          1.5 Continue to review and improve bike riding and walking asset
          management systems and programs by working closely with
          the community and promoting community members to report   ✓                                  ✓
          maintenance issues to Council that enables maintenance issues to
          be quickly resolved.

          1.6 Work with and seek funding from TMR and other agencies to
          deliver projects identified as part of the NCWSIP, as well as Priority   ✓                   ✓
          Cycle Network (PCN) projects. Relevant NCWSIP outcomes are to
          be provided to TMR for inclusion in their network planning.

          1.7 As part of the broader Transport Strategy implementation,
          investigate additional funding, including new revenue streams, to   ✓
          increase Council spend on delivering the NCWSIP.
         Table 7: Action 1. Deliver and maintain a safe and connected network
















      22